Cable opening delayed Harvey Dawkins2023-03-21T16:33:10+00:00 Sorry cable opening delayed We are unable to open Air and Tech Cables for the first weekend of the season. We are having a nightmare getting critical parts. The parts we require have a 28 week lead time due to shortage of components. We have had to search high and low to source refurbished parts which are costing us 2.5 times the cost of new parts and the delivery date has been rearrange on us 4 times ! We are expecting the parts in late March and we have an engineer booked for the first week of April. We will update you as we know more. Share this post Facebook Twitter LinkedIn Google + Email Author Harvey Dawkins